Configuring the Power Schedule

  1. Go to Control Panel > System > Power > Power Schedule.
  2. Select Enable schedule.
  3. Perform any of the following tasks.

    Task

    User Action

    Add a scheduled action

    Note:

    One schedule is shown by default.

    1. Click Add.

    2. Select the following.

      • Action: Select whether you want to shut down, restart, or turn on the NAS.

      • Schedule Type: Select the frequency of the action.

      • Hour and Minute: Select the time of day to perform the action.

    Remove a scheduled action

    1. Select one or mutliple schedules.

    2. Click Remove.

  4. Optional: Select Postpone scheduled restart/shutdown when a replication job is in progress.
  5. Click Apply.